This site is a developmental version of Wiki Law School. To go to the production site: www.wikilawschool.org

Austin Instrument v. Loral: Difference between revisions

From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
No edit summary
Line 13: Line 13:
Facing with a dilemma of losing the Navy contract, Loral acceded to the higher demanded price by Austin for the 1965 sub-contract. However, after the delivery to the Navy, Loral sought to recover the price increases.
Facing with a dilemma of losing the Navy contract, Loral acceded to the higher demanded price by Austin for the 1965 sub-contract. However, after the delivery to the Navy, Loral sought to recover the price increases.
|procedural_history=Austin sued Loral for the higher price for the 2nd (1966) contract.
|procedural_history=Austin sued Loral for the higher price for the 2nd (1966) contract.
At the same time, Loral sued Austin on the ground of [[Contracts_Ayres/9th_ed._Outline#F._Duress|economic duress]].
The trial court awarded the sum Austin requested.
|issues=Does 1 party's threat to breach an agreement by withholding goods unless the other party agrees to some demand constitute economic duress sufficient to void the agreement?
|holding=Yes. A party's threat to withhold goods unless the other party accedes to its demands constitutes economic duress.
|case_text_links={{Infobox Case Brief/Case Text Link
|case_text_links={{Infobox Case Brief/Case Text Link
|link=https://nycourts.gov/reporter/archives/austin_loral.htm
|link=https://nycourts.gov/reporter/archives/austin_loral.htm

Revision as of 15:29, July 28, 2023

Austin Instrument v. Loral
Court New York Court of Appeals
Citation
Date decided July 6, 1971

Facts

A defense contractor who failed to deliver might have blown its chance of getting another contract with the U.S. military.

In 1965, Loral Corp. ("Loral") won a $6 million contract with the U.S. Navy to manufacture & deliver radar sets. In turn, Loral award Austin Instrument, Inc. ("Austin") a sub-contract for 23 of the 40 radar components.

In 1966, the next year, Loral received another contract from the Navy &, again, sought bids for the same 40 components.

Austin informed Loral that it would stop the current delivery unless the new 1966 contract for all 40 components would be for a higher price. After this ultimatum, Austin stopped delivering to Loral.

Facing with a dilemma of losing the Navy contract, Loral acceded to the higher demanded price by Austin for the 1965 sub-contract. However, after the delivery to the Navy, Loral sought to recover the price increases.

Procedural History

Austin sued Loral for the higher price for the 2nd (1966) contract.

At the same time, Loral sued Austin on the ground of economic duress.

The trial court awarded the sum Austin requested.

Issues

Does 1 party's threat to breach an agreement by withholding goods unless the other party agrees to some demand constitute economic duress sufficient to void the agreement?

Holding

Yes. A party's threat to withhold goods unless the other party accedes to its demands constitutes economic duress.

Case Text Links