This site is a developmental version of Wiki Law School. To go to the production site: www.wikilawschool.org

Peevyhouse v. Garland Coal and Mining Co.: Difference between revisions

From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
(Created page with "'''Facts''': Defendant contracted with Plaintiff to use Plaintiff's land as a coal mine, and after such use to clean up the area, which was estimated to have cost Defendant $29,0...")
 
No edit summary
 
Line 1: Line 1:
'''Facts''': Defendant contracted with Plaintiff to use Plaintiff's land as a coal mine, and after such use to clean up the area, which was estimated to have cost Defendant $29,000 to conduct. Defendant didn't clean up.
{{Infobox Case Brief
|court=Supreme Court of Oklahoma
|citation=382 P.2d 109 (1962)
|subject=Contracts
}}
'''Facts'''


'''Procedural History''': Plaintiff sued for $25,000 damages for breach of contract. Jury awarded $5,000 to Plaintiff (more than the value of the entire farm, even after the clean up is done).
Plaintiff contracted with defendant coal mining company to allow them to use plaintiff’s land in excavating a coal vein. In the contract, defendant specifically agreed to perform certain restorative and remedial work at the end of the contract. The work would involve moving many thousands of yards of dirt, a cost estimated to be about $29,000, while the improvement to the land was estimated at only $300.


'''Issue''': What amount of damages is owed to Plaintiff? Expected damages would be the amount to clean up ($29,000) and reliance damages would be the loss of value to the farm (estimated at a couple hundred dollars).


'''Holding''': Damages are limited to diminution of value resulting from the non-performance.
'''Procedural History'''


'''Reasons''': If the work to be done is "disproportionate to the end to be attained" the value rule should be followed. The provision that was breached was merely incidental to the main provisions of the contract.
Verdict for plaintiffs in the amount of $5,000, only a fraction of the cost of performance.


'''Judgment''': Award for damages should be reduced to $300.
 
[[Category:Cases:Contracts]]
'''Issues'''
 
Whether the damages should be limited to the difference in the value of the land or to the cost of the remedial work defendant agreed to do.
 
 
'''Judgment''' for plaintiff for $300.
 
 
'''Reasoning'''
 
The cost of performance is the proper measure of damages if it does not involve unreasonable economic waste. Where the defect in material or construction is incidental to the main purpose of the contract and one that cannot be remedied without an expenditure for reconstruction disproportionate to the end to be attained, the value rule should be followed.
 
 
'''Dissent'''
 
The measure of damages should be the cost of performance because that is what the contract calls for and there is freedom of contract.

Latest revision as of 00:51, April 27, 2020

Peevyhouse v. Garland Coal and Mining Co.
Court Supreme Court of Oklahoma
Citation 382 P.2d 109 (1962)
Date decided

Facts

Plaintiff contracted with defendant coal mining company to allow them to use plaintiff’s land in excavating a coal vein. In the contract, defendant specifically agreed to perform certain restorative and remedial work at the end of the contract. The work would involve moving many thousands of yards of dirt, a cost estimated to be about $29,000, while the improvement to the land was estimated at only $300.


Procedural History

Verdict for plaintiffs in the amount of $5,000, only a fraction of the cost of performance.


Issues

Whether the damages should be limited to the difference in the value of the land or to the cost of the remedial work defendant agreed to do.


Judgment for plaintiff for $300.


Reasoning

The cost of performance is the proper measure of damages if it does not involve unreasonable economic waste. Where the defect in material or construction is incidental to the main purpose of the contract and one that cannot be remedied without an expenditure for reconstruction disproportionate to the end to be attained, the value rule should be followed.


Dissent

The measure of damages should be the cost of performance because that is what the contract calls for and there is freedom of contract.