American Standard v. Schectman
From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
American Standard v. Schectman | |
Court | Appellate Division of New York |
---|---|
Citation | 439 N.Y.S.2d 529, 80 A.D.2d 318 |
Date decided | May 15, 1981 |
Facts
For 26 years, American Standard, Inc. ("Standard") operated a pig iron manufacturing plant near Niagara Falls, New York. However, in 1972, Standard closed its plant & hired Mr. Schectman who was a demolition & excavation contractor.
In accordance with the contract, Standard paid Schectman $275,000 to (1) remove equipment, (2) demolish structures, and (3) grade the land.
Schectman cut corners: he left the plant ungraded because grading would have cost him $90,000.Procedural History
Standard sued Schectman in the Erie Supreme Court for breach of contract. Schectman lost.
Issues
Can an injured party recover damages for the cost of completion of a construction contract?
Arguments
Schectman argued that Standard didn't suffer any damages. Schectman offered proof that Standard sold the land for $180,000.
Holding
Yes. A party can recover damages for the cost of completion of a construction contract if the breaching party fails to substantially perform the contract in good faith.
Case Text Links