American Standard v. Schectman

From wikilawschool.net. Wiki Law School does not provide legal advice. For educational purposes only.
Revision as of 12:56, July 24, 2023 by DeRien (talk | contribs)

American Standard v. Schectman
Court Appellate Division of New York
Citation
Date decided May 15, 1981

Facts

For 26 years, American Standard, Inc. ("Standard") operated a pig iron manufacturing plant near Niagara Falls, New York. However, in 1972, Standard closed its plant & hired Mr. Schectman who was a demolition & excavation contractor.

In accordance with the contract, Standard paid Schectman $275,000 to (1) remove equipment, (2) demolish structures, and (3) grade the land.

Schectman cut corners: he left the plant ungraded because grading would have cost him $90,000.

Procedural History

Standard sued Schectman in the Erie Supreme Court for breach of contract.

Arguments

Schectman argued that Standard didn't suffer any damages. Schectman offered proof that Standard sold the land for $180,000.